Which of the following are some of the requirements that personnel in the risk assessment team must meet?
Be experienced in the type of activity that is to be carried out.
Have knowledge of the equipment and systems that are to be worked upon.
Be aware of any relevant procedures and industry standards.
Be experienced in auditing and monitoring requirements.
Be qualified as a lead auditor.
回答
Which colour in the risk matrix represents levels of risks in the As Low As Reasonably Practicable (ALARP) region?
Yellow.
Green.
Red.
During the task, if you are uncertain or unsure about ANYTHING then you must stop the job and ask for advice.
True.
False.
What is the remaining risk called when prioritised risks have been controlled and lowered to a tolerable and acceptable level?
Residual risk.
Acceptable risk.
Tolerable risk.
Initial risk.
Assessed risk.
What are the five steps of risk management?
Identify.
Analyse.
Assess.
Control.
Monitor.
Investigate.
Eliminate.
Document.
回答
The success of the Risk Assessment depends a great deal upon how effectively it is communicated. Which three statements are correct?
A full discussion of the relevant risk assessment should take place during the Toolbox Talk or the Pre-job Safety Meeting.
Communication is critical to maintaining on-going hazard identification.
The personnel carrying out the task must thoroughly understand the hazards that may be present and the control measures that have been put in place.
Communication of the risk assessment only takes place in the last step of the risk management process.
The task may start even though not everyone is satisfied that the hazards have been correctly identified and the relevant control measures have been put in place.
回答
Dynamic risk assessment is important in constantly changing external and internal environments. What are the purposes of continually monitoring and reviewing the risk assessment while the work task is ongoing?
To detect any changes to the risks and risk criteria which may require revision of the risk control measures and priorities.
To ensure that controls are effective and efficient in both design and operation.
To identify the personnel responsible for any “near misses”.
To identify emerging risks.
回答
Which three elements does a Bow-tie diagram give a visual summary of?
What can cause an unintentional event or accident.
What the resulting events of such an accident could be.
What can cause an unintentional event or accident.
The frequency of an unintentional event or accident.
The areas in which personnel might be at risk of harm.
回答
There are no requirements to maintain risk assessment records.
False.
True.
In which step of the risk management process is the risk level compared against established risk criteria?
Assess.
Analyse.
Identify.
Control.
Monitor.
Тест оценивает навыки по оценке рисков и разработке мер по снижению возможных опасностей на борту судна.