Der Test besteht aus 80 zufälligen Fragen.
Gesamtzahl der Fragen zu diesem Thema: 147
Many large 2 stroke marine diesel engines are equipped with an auxiliary scavenge air blower. What is the purpose of this equipment?
To provide combustion air at start up, during manoeuvring and low load running when the turbocharger delivery is insufficient.
To allow full load running when the main turbocharger is defective.
To assist the main turbochargers in supplying combustion air when on full load.
To help cool the engine after it has been stopped.
What would be the correct form of response to the question: “What kind of assistance do you require?”
The correct form of response would be: “There is a fire onboard my vessel”.
The correct form of response would be: “My vessel has a fire in the accommodation and we require fire-fighting assistance”.
The correct form of response would be: “I need help on board with a fire and the smoke is very toxic”.
The correct form of response would be: “I need help as soon as possible”.
Why is it important to check the timing of diesel engine cylinder oil lubricators?
To ensure the piston is not covering the lubrication points and blocking the flow of cylinder lubricating oil into the cylinder.
To ensure cylinder lubricating oil enters the cylinders when the piston is in the required position.
To ensure the correct amount of cylinder lubricating oil is fed into the cylinders.
To avoid excess pressure in the cylinder lubrication system.
When you join a new ship, how are you informed about safety rules, alarm instructions and your own duties in case of an emergency?
By folder distributed to each crewmember.
By muster list exhibited in conspicuous places.
By alarm instructions in all crew cabins.
By oral instructions by the Captain.
PT-100 sensors are some times used with 3 or 4 wires. What is the reason for this?
Higher mechanical strength of the cable.
Because of power-consumption.
Higher measuring accuracy.
Modern slow speed, two stroke diesel engines often have locating pins or pegs to keep the piston rings in a fixed position. Why is this arrangement used?
The piston ring gaps can be kept in line to control the gas pressure on each of the rings.
The piston rings are more difficult to lubricate because of the slow operating speeds and will wear more quickly if they are allowed to rotate.
It avoids the risk of the ends of the piston rings being forced out by the gas pressure and catching on the scavenge ports.
It ensures the rings cannot be mixed up and that they are fitted in the correct order on the piston.
What is likely to be the cause of black smoke from a diesel engine exhaust seen at the funnel?
Engine is burning some lubricating oil.
Incomplete combustion of the fuel.
A power card taken from a diesel engine cylinder using a mechanical indicator has a flat top. Which of the possible actions given in the options is most likely to correct this irregularity on the power card?
Lengthen the cord for the indicator drum drive.
Change the indicator spring for one with a higher rating.
Shorten the cord for the indicator drum drive.
Lubricate the indicator piston and cylinder.
If a refrigeration system contains air, how would you remove it from the system?
Pump the system down to the evaporator and keep the fan running until the evaporator is at ambient temperature and vent off the air from the top of the evaporator.
Stop the compressor and vent the air from the crankcase.
Pump the system down to the condenser, continue cooling water flow until the condenser is at the same temperature as the cooling water and vent off the air from the top of the condenser.
Stop the compressor and undo a pipe coupling at the highest point in the system to vent off the air.
A detector that is activated by a rise of temperature is:
While alongside at a repair berth a new section of seawater pipe has been fabricated in a shoreside workshop from drawings supplied by the vessel. During fitting of the pipe by ship’s engineers it is noted that the pipe is too short leaving a gap of about 8 mm between the flange faces. What action should be taken to remedy this problem?
The pipe should be returned to the shoreside workshop for modification or to be remade to the correct dimensions.
The ships engineer’s should use extra long bolts and pull the flanges together.
The ship’s engineers should fit extra thick joints between the flanges to fill the gap.
The ship’s engineers should manufacture a spacer piece to fit the gap.
A seawater pump requires overhaul but there are no spare wear rings for the casing and impeller. It is decided that new wear rings will be fabricated onboard using the ship’s lathe. What would be the most suitable material to use to fabricate the rings onboard?
During an unmanned period on a UMS vessel the “low water level” alarm for the jacket cooling water system expansion tank activates. What action would you take as duty engineer?
Answer the alarm then block the alarm and change to manned engine room condition.
Answer the alarm then block the alarm function for later action and resume unmanned operation.
Answer the alarm and adjust the alarm set point for the water level in the expansion tank before resuming unmanned operation.
Answer the alarm, top up the tank and check the system for leakage before resuming unmanned operation.
What is the expansion ratio of the foam produced by the fixed low-expansion foam fire-extinguishing system of an engine room?
Greater than 20 to 1 but less than 50 to 1.
What do you understand by the order: “Move the pilot ladder to the other side?”
Move the pilot ladder to the other side, means: to move the pilot ladder further along nearer to the bow.
Move the pilot ladder to the other side, means: to rig another pilot ladder.
Move the pilot ladder to the other side, means: to change the position of the pilot ladder from the main deck to the fore deck.
Move the pilot ladder to the other side, means: to shift the pilot ladder to the opposite side of the ship.
Personnel in a high voltage switchroom and smell rotten eggs. What may this indicate?
Arcing at badly coupled bus bars.
Problems with a vacuum circuit breaker.
Problems with a gas (SF6) circuit breaker.
B Class divisions in ships are constructed so that they are capable of preventing the passage of flame to the end of a standard fire test held for:
Why is it important to check the timing of diesel engine cylinder oil lubricators?
To ensure the piston is not covering the lubrication points and blocking the flow of cylinder lubricating oil into the cylinder.
To ensure the correct amount of cylinder lubricating oil is fed into the cylinders.
To ensure cylinder lubricating oil enters the cylinders when the piston is in the required position.
To avoid excess pressure in the cylinder lubrication system.
A vapour compression refrigiration system is usually fitted with a number of devices to give protection and control of the system. Which of the methods given in the options should be used to test the high pressure cut out during routine maintenance and checking of the system?
Manually close each of the evaporator coils by switching off the electrical supply to the liquid line solenoid shut off valves and monitor the condenser pressure.
Close the condenser outlet valve and closely monitor the condenser pressure.
Gradually shut in the condenser cooling water valve or the condenser refrigerant inlet valve while closely monitoring the compressor discharge pressure.
Charge the system with refrigerant until the high pressure cut out operates.
An electrical power emergency source in a ship is required because:
It satisfies the SOLAS requirements for ship safety.
The main diesel generator(s) can be taken out of service for overhaul or repair.
It satisfies the need to be environmentally “friendly”.
The ships total load can be shared between main and emergency generators.
What is the correct name of the part highlighted in the illustration?
What is the correct name of the tool shown in the illustration?
During maintenance work on a compensated mechanical hydraulic governor air is drawn in to the hydraulic circuit after draining and flushing out the unit. Which of the actions given in the options is most likely to assist in the removal of the air from the system?
With the governor in operation open the compensation needle valve to introduce instability and disturb the engine load to make the governor hunt.
Overfill the governor with fresh oil to force all of the air out.
Drain the governor again and slowly refill with fresh oil.
With the governor in operation close the compensation needle valve and disturb the load to make the engine hunt.
What do you call the wide rung on a pilot ladder that prevents the ladder from twisting?
The wide rung on a pilot ladder that prevents it from twisting is called a “Spreader”.
The wide rung on a pilot ladder that prevents it from twisting is called a “Wide step”.
The wide rung on a pilot ladder that prevents it from twisting is called a “Long rung”.
The wide rung on a pilot ladder that prevents it from twisting is called a “Ani-twist rung”.
What type of construction material should be avoided regarding fire protection purposes? (SOLAS II-2/2.2.3).
All combustible materials.
All uncovered wooden materials.
What acton is required if the crankcase relief valve on an air compressor is operating and emitting an air and oil mixture?
Increase the lift pressure of the relief valve.
Overhaul the compressor unit.
Increase the flow of cooling water to the compressor and intercooler.
Place a drip can beneath the valve to collect any escaping oil.
The mandatory color of a hand flare is:
What is the main effect on lubricating oil of operating for long periods at excessively high temperature?
It will cause the oil to oxiside, increasing the viscosity.
It will cause the oil to oxidise, reducing the viscosity.
It will cause the oil to evaporate, increasing consumption.
It will change the flashpoint of the oil.
What is the correct name of the part highlighted in the illustration?
For two generators running in parallel, their share of additional load (kW) will be determined by the:
Voltage droop setting on each AVR.
Governor droop settings on each prime mover.
The temperature difference between the generator rotors.
The power factor of the additional load.
What is the best method to use to remove heavy scale and fouling from the plates of a heat exchanger?
Use high-pressure cleaner with abrasive additives.
Soak the plates in recommended cleaning solution and then use a soft brush or pressure cleaner.
Use wire-brush metal scrapers and chipping guns.
What will be the probable outcome if the amplification is set too high on a controller?
The process will oscillate and get out of control.
The set-point will change.
The process response will be very slow.
A piston rod retaining nut needs to be tightened during maintenance on the main engine. Which of the given methods should be used to ensure it does not come loose in service?
Tighten it as tight as possible using a flogging spanner and a hammer.
Tighten it 10 % more than the manufacturer’s recommendation using a torque wrench.
Tighten it to the manufacturer’s recommendations using a torque wrench.
Tighten it as tight as possible using a spanner and extension pipe.
What function is this operational amplifier circuit performing?
Modern slow speed, two stroke diesel engines often have locating pins or pegs to keep the piston rings in a fixed position. Why is this arrangement used?
The piston ring gaps can be kept in line to control the gas pressure on each of the rings.
The piston rings are more difficult to lubricate because of the slow operating speeds and will wear more quickly if they are allowed to rotate.
It avoids the risk of the ends of the piston rings being forced out by the gas pressure and catching on the scavenge ports.
It ensures the rings cannot be mixed up and that they are fitted in the correct order on the piston.
What is the purpose of the ODME (Oil Discharge Monitoring Equipment) printer?
To prove that oil has been pumped overboard according to regulations.
To prove fault conditions in the ODME.
To prove that the ODME system has been used.
What is the most important task after carrying out any major overhaul on a diesel engine?
Start the auxiliary blower to ventilate the engine so that it has sufficient fresh air for starting.
Start the engine to check the direction of rotation.
A thorough check inside the engine to make sure all tools and cleaning rags have been removed.
Repair any damaged paint work on the engine.
A mechanical seal, consisting of carbon and ceramic seal rings, is to be fitted to a centrifugal pump shaft. What is the most likely result of not being extremely carefull when fitting this type of seal?
The spring and bellows for the seal can be easily damaged.
The rubber O rings for the seal can be easily damaged.
The seal rings are hard and may score the pump shaft.
The seal rings are brittle and can be easily chipped or damaged.
What could cause diesel engine lubricating oil to appear cloudy with a slightly “milky” colour?
Fuel contamination of the system.
High temperature of the oil.
Water contamination of the system.
An auxiliary engine is fitted with a duplex type lubricating oil filter. The in-use element requires changing. What procedure should be used to fit the new element?
With the engine running, position the changeover cock so that both filters are in use to reduce the pressure before.
With the engine running, shut off the filter inlet and quickly fit the new element.
The engine must be stopped to fit a clean filter element.
With the engine running, change over to the other filter after priming it and replace the dirty element after checking there is no pressure on dirty filter housing.
You are witnessing someone about to faint. What are the symptoms?
The person may be very pale, and pulse is slow at first and weak.
The pulse is very fast and the person is getting cold.
The person starts to talk a lot and seems superactive.
The two instruments necessary for generator synchonising are:
kW meter and frequency meter.
Voltmeter and synchroscope.
Synchroscope and kVar-meter.
Amp-meter and volt-meter.
What is the correct name of the tool shown in the illustration?
What is the correct name of the part highlighted in the illustration?
It is common practice to connect a resistor over an alarm contact (see diagram) in many applications. Why is this connection used?
To monitor the cable/wires for break.
To stabilise power consumption.
To avoid sparks on the contacts when opening and closing.
Enable measuring the total resistance of the circuit.
What does the term “Dead Ship” mean?
“Dead Ship” means that the ship cannot make way through the water.
“Dead Ship” means that the ship is aground.
“Dead Ship” means that the machinery and boilers are inoperational due to lack of electrical power.
“Dead Ship” means that auxiliary machinery is not operational.
With two alternators running in parallel, and one is to be disconnected. The first step is to:
Remove the load from the alternator to be stopped.
Increase the frequency on the switchboard.
Trip the main circuit breaker.
Make sure the load is evenly shared.
In a low pressure auxiliary boiler, what would be considered to be the maximum allowable chloride level of the boiler water?
Which ships does the ISM code apply to?
All passenger ships, all cargo ships of 500 GRT or above.
During a bomb search, which of the following is an important principle to follow?
Throw any suspicious items overboard.
Try to reach behind bulkheads to find a bomb.
Do not touch any suspicious packages.
Know exactly what a bomb looks like.
Which part of the crankshaft of a modern large two stroke diesel engine is most likely to be the origin point for crack initiation during service and therefore needs the greatest attention during maintenance inspection?
The dowel pins and dowel holes.
During maintenance of a pneumatically operated, diaphragm actuated control valve the diaphragm is found to be split. Select, from the options given, a suitable material to use to make a temporary replacement if there is no spare diaphragm available.
Natural rubber sheet of approximately the same thickness and elasticity as the original diaphragm material.
Cotton reinforced rubber insertion sheet of smaller thickness but similar strength as the original diaphragm material.
Natural rubber sheet of greater thickness and lower elasticity as the original diaphragm material.
Cotton reinforced rubber insertion sheet of approximately the same thickness but less elasticity than the original diaphragm material.
During an unmanned period on a UMS vessel the “low water level” alarm for the jacket cooling water system expansion tank activities. What action would you take as duty engineer?
Answer the alarm then block the alarm function for later action and resume unmanned operation.
Answer the alarm then block the alarm and change to manned engineroom condition.
Answer the alarm and adjust the alarm set point for the water level in the expansion tank before resuming unmanned operation.
Answer the alarm, top up the tank and check the system for leakage before resuming unmanned operation.
What are the lists called that give the position and task during a lifeboat drill for all persons on board the ship?
It is recommended that every prospective seafarer should, before being employed in a sea-going ship, receive proper training in personal survival techniques. In respect of such training several recommendations are made. Answer the question: “To whom should training in personal survival techniques be given?”
Which of the following fittings shall be provided to all lifeboats?
A manually controlled lamp fitted on the outside.
A remotely operated steering arrangement.
An electric power starting system for the propulsion engine with one rechargeable energy source.
Permanent boarding arrangements on both sides to enable persons in the water to board the lifeboat.
What is the correct name of the tool shown in the illustration?
What is generally considered as the minimum safe time period before opening a crankcase door after the oil mist detector alarm has activated and the engine has been stopped?
After at least 20 minutes.
After at least 5 minutes.
After at least 10 minutes.
On finding a person apparently unconscious in a High Voltage switch room, which of the following should be done?
Raise alarm then drag the victim clear so that they cannot reach live parts while receiving aid.
Check if the victim is in contact with live parts and if not apply first aid.
Raise alarm, identify means of isolation and apply before approaching victim.
Trip all breakers and approach victim.
What is the main reason for keeping engine lubricating oil viscosity within recommended limits?
To reduce system pressure losses.
To ensure the strength of the oil film is sufficient to keep lubricated surfaces apart.
To neutralise any acids that may form.
The circuit consists of two inductors, L(1) = 6 H and L(2) = 12 H, connected in parallel. Calculate the equivalent L(S) of the two inductors.
A section of seawater pipe has been removed for maintenance. When refitting the pipe after completing the work the bolt holes in the flanges are found to be misaligned. What procedure should be followed to finish the work?
Adjacent pipework should be slackened off to allow the pipe to be aligned. Any incorrectly positioned brackets should be adjusted after the pipe is refitted.
Use a chain block to pull the pipe flanges into alignment and leave it in place after the bolts are fitted to avoid overstressing the bolts.
Use wooden wedges to force and hold the pipe into the correct position and then fit the bolts.
Force the pipe into position and then hammer the bolts into the holes to hold the pipe flanges into alignment.
As part of the regular maintenance for a paramagnetic oxygen analyser used for measuring the oxygen content of exhaust gas it is important to keep the sample line filter as clean as possible. Why is this necessary with this type of instrument?
The filter may rupture due to the high pressures generated by the sample pump.
Pressure variations in the sample chamber can cause errors so restrictions must be kept to a minimum.
The pressure drop across the filter may damage the sampling pump.
A high flow rate is required in order to deflect the sensing element.
An earth fault exists on the blue line of a 100 A bilge pump circuit. A second earth fault occurs on the yellow line of a 10 A ventilation fan circuit. Both systems are supplied from the ship’s 440 V supply. The likely outcome is that:
A short circuit occurs between earth faults and the ventilation fan fuse blows.
An open circuit occurs between earth fault and both motors trip out.
A short circuit occurs between earth fault and the bilge pump fuse blows.
Both motors trip out on overload.
When a fire breaks out in the accommodation, cargo holds or on deck, who is in charge of the fire fighting operations?
The first officer arriving at the scene.
The first person arriving at the scene.
The person who is designated in the muster list.
Many large slow speed diesel engines operating on heavy fuel oil have a fuel injection system which features Variable Injection Timing. How does this affect engine operation?
VIT increases engine efficiency by automatically maintaining the maximum cylinder pressure over the entire load range.
VIT increases engine efficiency by automatically maintaining the maximum cylinder pressure over part of the load range.
VIT improves engine operation by automatically controlling the start of fuel injection when it detects a poor quality fuel.
VIT allows the ship’s engineers to alter the injection timing for each load setting with a simple single adjustment of the fuel rack.
A large electric motor is being removed from a main seawater pump with the aid of the engine room crane. Which is the best method of starting the lift from the options given?
Use the full hoist facility on the crane to “break” the motor free after slackening all of the retaining bolts.
Use the “inch up” facility on the crane to “break” the motor free after slackening all of the retaining bolts.
Use a suitable chain block suspended from the crane hook to “break” the motor free after slackening all of the retaining bolts.
Use the full hoist facility to lift the motor clear in one action after removing all of the retaining bolts.
The responsibility for safety and security rests with everybody on board the vessel. General house-keeping rules should be followed. Which of the listed rules is the most important?
Do not carry lighters or matches when working outdoors.
Always use gloves when using grinding machines.
Keep tools within easy reach during work.
Keep your working area clean and tidy.
Why may wearing sweat rags slung round your neck when working in the machinery spaces be hazardous?
The rags may cause sweat rash.
The rags may cause you to get too hot and faint.
The rags may be soaked with oil and catch fire.
The rags may be caught by running machinery or power tools.
Which of the following is not a principle of heat transfer utilised in an oil fired steam boiler?
Is it necessary to cool the samples taken from a diesel engine cooling water system before carrying out tests to determine the concentration of treatment chemicals?
No, the test should be carried out at system temperature.
Yes, the samples should be cooled to approximately 25 °C.
Yes, the samples should be cooled to approximately 50 °C.
No, the samples should be heated to approximately 95 °C.
You are starting to get low on water in the lifeboat. What should you do?
Mix sea water with 50 % fresh water.
An air compressor is being refitted in the engine room. The compressor and motor are coupled using a flexible coupling and are mounted on a common “skid” which fixed to the deck with resilient mountings. Which of the statements, from the options given, relating to the alignment of the motor and compressor is true?
Shims should be fitted between the motor and compressor feet and the skid to ensure correct vertical, horizontal and parallel alignment of the coupling halves before it is bolted up.
As long as the two coupling halves are at the same height the flexible coupling will accommodate any horizontal misalingment of difference in the gap between the coupling faces.
The compressor and motor can just be placed directly on the common skid as they will probably be closely aligned anyway.
Machines using flexible couplings and resilient mountings do not need to be aligned. That is why they have flexible and resilient elements fitted.
This device can detect a package of drugs inside a large delivery of ship’s stores. What is it?
The correct time to synchronise is usually taken to be when the synchroscope reaches the “5 to 12” position and is rotating slowly clockwise. This to allow for:
Generator phase difference error.
Circuit breaker operating time.
Synchroscope pointer time lag.
What do you understand by: Bitter end?
Bitter end means: the end link of an anchor cable that is secured within the chain locker.
Bitter end means: a foul taste at the end of a meal.
Bitter end means: to the very last moment.
Bitter end means: the toggled end of a lifeboat painter.
Which muscle is the most persevering one in the body?
What type of component does this graphical symbol illustrate?
Pressure-reducing regulator.
Which of the following voltage levels would be regarded as high voltage likely to be found on a ship?
Under which circumstances should a sprinkler head of a common fixed sprinkler fire-extinguishing system be activated?
When the smoke density exceeds 12,5 % obscuration per minute, but after the corresponding alarm is acknowledged and assessed at the control panel.
When the temperature is within a range from 68 °C to 79 °C, but after the corresponding alarm is acknowledged and assessed at the control panel.
Automatically, when the temperature is within a range from 68 °C to 79 °C.
Automatically, when the smoke density exceeds 12,5 % obscuration per meter.