Le test comprend 80 questions aléatoires.
Total de questions sur ce sujet : 118
This figure shows a transformer, with two windings, N(1) = 2 000 and N(2) = 1 000 turns, on a common magnetic circuit. Assume that there is no energy loss in the transformer itself. Calculate the current I(2) when the current I(1) = 2 A.
The continuity resistance of a 100 m long × 25 sq. mm cable (rated at 100 A) is to be checked. Which of the following results would you anticipate?
Between 0,1 and 1,0 M Ohm.
Between 0,1 micro Ohm and 1,0 micro Ohm.
When performing electrical testing of a three phase motor, insulation resistance measurements may be influenced by which of the following?
Temperature, humidity and surface contamination.
Humidity, frequency and dampness.
Humidity, pressure and surface contamination.
Between 0,1 micro Ohm and 1,0 micro Ohm.
When considering instrumentation systems, what is the meaning of the expression “dead-band”?
The controller will not react to a process change in this range.
It will take some time before the controller will react to a change.
The controller will enter “sleep mode”.
The controller will not respond to adjustment of set-point.
A 250 V contactor has been fitted to a 220 V supply. Which of the following symptoms might be observed?
Contactor chattering (vibrating).
What is the correct operation of the slow-turning facility fitted to some large 2-stroke main propulsion diesel engines?
Slow turning should be set to operate automatically prior to engine start when engine has been stopped for 20 to 30 minutes during manoeuvring.
Slow turning should be set to operate automatically every 10 to 15 minutes when the engine is on standby.
Slow turning should be carried out immediately the duty engineer gets notice of standby from the bridge.
Slow turning should be set to operate automatically at finish with engines to allow the engine to cool down evenly.
Some ships generate electrical power at 440 Volts, but then step up this voltage to supply specific electrical equipment. One common example, may be to feed a large bow thruster. Why is this done?
A large bow thruster will draw very large currents at low voltage. Being typically remote from the generator, significant voltage drops would occur at low voltage.
The shipyard could not purchase High Voltage generating plant at the time of manufacture, so they used what was available at the time.
The overall ship’s electrical load does not justify High Voltage generating plant. This method allows more power to be delivered to the bow thruster at low running cost.
Manufacturers can supply High Voltage bow thrusters at less cost, and the power factor is improved.
Two reference points for pressure exist, absolute zero and atmospheric pressure. What are pressures measured relative to absolute zero called:
A medium speed diesel engine which is supported on a steel chocking system has had repeated problems with two of the chocks at the end of the engine on the port side becoming slack. This has led to some fretting damage to the bedplate and tank top in that area. What action should be taken to affect a cost effective permanent repair?
Tighten the holding down bolts in that area to 150 % recommended load to prevent further slackening and fretting.
Replace the complete steel chocking system with one using resilient mounts to accommodate movement and avoid further incidents of fretting.
Replace the damaged chocks with resin based chocks of an appropriate size.
Replace the complete steel chocking system with a resin based system.
What kind of electrolyte is used for Nickel-iron batteries?
Solution of sodium and water.
Solution of zinc-carbon and water.
Solution of sulphuric acid and water.
Solution of potassium hydroxide (KOH) and water.
Low voltage ships tend to have insulated neutral systems. What is the reason for this?
In the event of an earth fault vital equipment will not trip.
It’s easier to detect faults.
If the neutral is not insulated, then it may short to other conductors.
It’s more effective than insulating the live conductor.
A draw card obtained from a cylinder of a large 2 stroke diesel engine shows that both cylinder compression and maximum pressures are low. Cards from other cylinders indicate normal operation. What is the likely cause of this problem?
Faulty cylinder component (piston rings, liner, etc.).
Excessive cooling of the charge air.
Faulty high pressure fuel pump.
In the context of an automated process control system, what is understood by the expression Master Controller?
The primary controller in a cascade control system.
The captain’s controller.
State of the art controller.
The best possible control system.
You are in charge of a night bunkering operation. The delivery rate from the supplier is high and you are filling six tanks simultaneously. You lose track of the progress of the operation and feel that you are losing control of the situation. What action should you take?
Stop bunkering, and establish facts, before bunkering is resumed.
Open more tanks to slow down the filling rate of individual tanks.
Prepare yourself and the crew for an overflow.
Request a reduction in the delivery rate to try and gain some time.
What is the best way to avoid pollution from small oil-spills aboard a ship?
Contain any oil-spill onboard the ship.
Have dispersing chemicals ready for use in case of oil-spill.
Rig an oil boom around the ship.
Have sawdust ready for use.
Some fuel oil and lubricating oil separators have a facility to control the back pressure of the clean oil outlet during start up and operation. What is the purpose of this control function?
To help to maintain the oil/water interface at the correct position.
To reduce the amount of sealing water required during operation.
To control the amount of fuel passing through the separator.
To assist in discharging the bowl contents during the sludge cycle.
A two step controller (open/close) has failed and the only available spare controller is a P+I controller. Select, from the options given, how the P+I controller could be set up to achieve approximate two step control.
Set the proportional band to maximum width and the integral action to minimum (repeats per minute).
Set the proportional band to minimum width and the integral action to maximum (repeats per minute).
Set the proportional band to minimum width and the integral action to minimum (repeats per minute).
When considering instrumentation systems, what is a typical symptom of a fault with the span of an instrument?
100 % output is accurate, but Zero-point is wrong.
Zero-point and 100 % are correct, but not at mid-range.
Zero-point is accurate, but 100 % input is not giving 100 % output.
Worn piston rings are allowing a small amount of piston blow-by on a 2-stroke main diesel engine cylinder, but due to the circumstances, it is not possible to stop and do a piston overhaul. What is the correct, temporary action to take?
Increase cylinder oil feed rate slightly and monitor the scavenge space drains.
Continue to operate the engine as normal.
Increase cylinder oil feed rate to the maximum.
Continuity testing of a delta connected three phase induction motor yields the following results; U-V = 3 ohms, V-W = 3 ohms, W-U = 6 ohms. Which of the following is the likely condition?
Open circuit winding between W and U.
Partial fault between W and U.
Short circuit between V and Earth.
Short circuit between W and U.
A 6-Volt DC relay is to be used with a 12-Volt power supply. The relay requires a current of 0,1 Amp. What is the series resistance required?
The pyrotechnics used to transmit visual signals to other vessels, boats or aircrafts are of the following type:
All of the below mentioned.
The fuel consumption for the main diesel engine has gradually increased over a period of a few months. All system pressures and temperatures appear normal. From the options given, choose the one which is the most likely cause of this:
Sea water temperature changing.
In the circuit diagram shown the starter connects between which terminals?
How is a Safety Management Certificate obtained?
Ship owner has Document of Compliance issued, and vessel is assessed and holds all statutory certificates.
RSS issue SMC with Register.
Vessel is surveyed by MCA and certificate issued.
Ship owner is authorised to carry out internal audits and issue SMC.
The torsion meter for the main propeller shaft is reading high. The torque is sensed using the angle of twist principle with two clamp rings attached to the shaft at a fixed distance, with stationary proximity switches for measuring the angle of twist and also shaft speed fixed to a rigid stool. What is the most likely cause of the high reading?
Circumferential slip of the after clamp ring in the opposite direction to shaft rotation.
Axial slip of one of the clamp rings to bring them closer together.
Axial slip of one of the clamp rings to move them further apart.
Which of the following is typical for a feed-forward control system?
Mathematical calculation of the system response.
Easy to obtain a perfect control.
Control of the process inlet side.
The process continually oscillates.
A galley hot plate uses a Nichrome/Magnesium Oxide heating element and is to be tested before being put into service for the first time. An insulation resistance test yields a reading of 0,3 M Ohm. Which action should be taken?
Apply reduced voltage to the element for a few minutes. Then retest and if ok put into service.
Put the element into service.
Wash the element in a degreasing agent. Then retest and if ok put in into service.
How will continuous low load operation influence the time between overhauls, tbo, for the cylinder covers and associated valves of a 4-stroke diesel engine?
Reduce the time between overhauls due to increasing fouling.
Increase the time between overhauls since the engine is not working as hard.
Increase the time between overhauls since fuel injectors work better at low load so combustion will be improved and the maintenance will be reduced.
Why is an automatic slow turning feature included in the start air system of many large 2 stroke diesel engines?
To avoid damage during start of the engine in case water or other liquid has gathered in the cylinders during an extended stop.
To reduce the start air consumption during start up of the engine.
To check that all indicator cocks are closed before starting engine.
To fill the cylinders with sufficient fresh air to ensure a safe start of the engine.
A transformer overheats while taking a shore supply. Which is the likely cause?
The operating mode of a pyrotechnic signal depends essentially on:
Instructions or diagrams printed on its casing by the manufacturer.
The weather conditions of the moment.
The fact that the user is on board a liferaft, a lifeboat or ship.
A definite standard process.
The coil of a 12 V, 120 mA DC relay must be connected across a 24 V supply. What action should be taken?
Install a 100 Ohm resistor in parallel with the coil.
Install a 100 k Ohm resistor in parallel with the coil.
Install a 100 k Ohm resistor in series with the coil.
Install a 100 Ohm resistor in series with the coil.
In which of the following automated control processes will the time constant be of minor importance?
In case of pollution in US waters, do you always have to notify the National Response Center (OPA-90)?
Yes, within thirty (30) minutes.
Yes, within three (3) days.
No, not if the local US State Authority is correctly notified.
No, only the shipowner can notify NRC.
A medium speed diesel engine is used to drive a controllable pitch propeller through a suitable clutch and reduction gearbox. What should the propeller blade attitude normally be after the engine is started and before the clutch can be engaged?
The blades should be in the zero pitch position.
The blades should be in 20 % pitch position.
The blades should be in the full astern position.
The blades should be in the full ahead position.
What should be the healthy continuity resistance of a 220 V, 2,2 kW, 10 A heating element, when checked near to it’s rated operating temperature?
What type of dynamic forces may cause indent in plating on forecastle deck and main deck in way of pillars inside forecastle?
Impact pressure forces in way of abrupt or flared bow.
Forces created by waves on the forecastle.
Slamming in way of flat bottom forward of light draught.
Pressure forces caused by green water on deck.
In terms of automated control systems, what is typical for a continuous control system?
It is possible to predict the control mathematically.
The control valve will always be changing position.
It is not possible to have a stable process.
The output signal is equal to the input signal.
It is the Master’s responsibility to ensure that:
Concerned personnel carry out the on-board training programme effectively.
All information regarding the onboard training is given to the ship manager.
Safety equipment is not used during the training.
Life jackets are worn during every training.
The circuit diagrams illustrate four different methods of wiring between a Pt 100 temperature sensor and its signal processing electronics. Which of the wiring methods gives the best measuring accuracy?
When considering instrumentation systems, what is a typical symptom of a fault with the span of an instrument?
100 % output is accurate, but Zero-point is wrong.
Zero-point and 100 % are correct, but not at mid-range.
Zero-point is accurate, but 100 % input is not giving 100 % output.
The main engine is running steady with an average exhaust gas temperature of approximately 350 °C. What would be a typical alarm/slow down setting for the cylinder exhaust gas temperature deviation from the average?
In a distress situation, how many times or for how long should the emergency alarm signal be sounded?
Until all crew members and passengers have reported to their respective muster stations.
Until the signal “risk is over” or the order “abandon ship” is given.
When should a crew member joining a ship for the first time be given some training and instructions in the use of the ship’s fire-fighting appliances?
As soon as possible but not later than 2 weeks after he joins the ship.
As soon as possible but not later than 2 days after he joins the ship.
As soon as possible but not later than 24 hours after he joins the ship.
A transformer rated at 22 kVA, 440/220 Volts, 60 Hz, is used to step down the voltage to a lighting system. The low tension voltage is to be kept constant at 220 Volts. What load impedance connected to the low-tension side will cause the transformer to be fully loaded?
A 6-Volt DC relay is to be used with a 12-Volt power supply. The relay requires a current of 0,1 Amp. What is the series resistance required?
Which one of the listed requirements regarding abandon ship drills corresponds to present SOLAS regulation?
Each lifeboat shall be launched, and maneuvered in the water with its assigned crew at least once every three months during an abandon ship drill.
Drills shall be conducted when the ship is in a harbour.
All lifeboats shall be lowered during drills.
Oil analysis results for a sample of diesel engine lubricating oil show a high level of tin. What could be the possible cause?
Debris from damage to a white metal bearing.
Debris from damage to a rolling contact bearing.
Cylinder oil contamination of the lubricating oil system.
Debris from fretting between bearing housing parts.
The temperature control for a hot water system is very erratic with the temperature gradually rising and then suddenly falling and vice versa even though system demand is fairly constant. Which of the options given is the most likely cause of this problem?
Control valve gland is over tightened.
Controller integral action reset time is too fast.
Control valve actuator diaphragm is ruptured.
Control air pressure supply is too low.
When the cable length exceeds approx. 10 meters we normally have to, in case of a Pt 100, in some way compensate for the cable resistance. Do we also have to do this if we choose to use a T802 temperature sensor?
Depends on temperature to be measured.
The fuel tank contents gauges onboard a vessel are of the air bubble and bell type. The gauges are calibrated for a different fuel type to the actual fuel in the tanks. When correcting the actual contents of the tanks from the gauge readings which of the parameters given in the options is the most important?
Routine maintenance insulation testing of a three-phase induction motor should cover which measurements?
U1-U2, V1-V2, W1-W2, U-E, V-E, W-E.
U-E, V-E, W-E, U-V, V-W, W-U.
How often should the lifeboat wire falls be turned and renewed?
Turned at intervals of not more than 30 months and renewed every 5 years.
Renewed every three years.
Turned every 30 months and needs only to be renewed if the wire is in poor condition.
Turned every 2 years and renewed every 4 years.
Why is it important that the correct tension is maintained in a diesel engine timing chain?
Correct tension ensures that the chain and associated equipment is within normal loading limits.
Correct tension ensures that there is absolutely no vibration in the chain.
Correct tension ensures that the fuel and valve timing are correct.
Correct tension ensures that the chain is correctly lubricated.
Sometimes an early warning of failure in High Voltage switchboards may be an unpleasant smell. If the switchboard uses gas circuit breakers, which of the following may indicate a potential problem?
After a couple of hours of operation the failure alarm sounds for a heavier fuel oil purifier which is operating on a timed automatic sludge cycle. Upon investigation the purifier is found to be running slowly and when opened up the casing and sludge outlet is heavily fouled with sludge in contact with the bowl. From the options given what is the most likely cause of this problem?
The heavy fuel is unstable leading to excessive high viscosity sludge formation.
The dirty oil throughput is excessive.
The clutch for the drive shaft is worn and slipping.
The purifier bowl has not closed properly.
What type of dynamic forces may cause indent in plating on forecastle deck and main deck in way of pillars inside forecastle?
Pressure forces caused by green water on deck.
Impact pressure forces in way of abrupt or flared bow.
Forces created by waves on the forecastle.
Slamming in way of flat bottom forward of light draught.
Continuity testing of a delta connected three phase induction motor yields the following results; U1-V1 = 4 Ohms, V1-W1 = 4 Ohms, W1-U1 = 4 Ohms. What is the value of continuity resistance for each winding i. e. U1-U2?
Some automated control systems use a master controller and a slave controller. What is the meaning of “remote mode” related to a slave controller?
The slave controller can be turned by a hand carried remote controller.
The slave controller can be in any mode of operation.
The slave controller receives the set-point from the output signal of the master controller.
The slave controller can be turned from the engine control room.
Power is available at a three-phase motor starter, but nothing happens (at starter or motor) when the start button is operated. Which of the following is a likely cause?
Open circuit in one of the motor cables.
Faulty overcurrent relay.
How does the maximum oil film pressure in a white metal journal bearing operating under full fluid film conditions compare with the pressure of the lubricating oil supply system?
The pressure is greater than the pressure in the lubricating system and varies with the journal load.
The pressure is the same as the pressure in the lubricating system regardless of the journal load.
The pressure is greater than the pressure in the lubrication and is constant regardless of the journal load.
The pressure is less than the pressure in the lubricating system and varies with the journal load.
The charge air pressure supplied to a diesel engine, which is normally 2,0 bar, is reduced to 1,5 bar. What will be the likely effect on the engine operation?
The performance of the engine will be reduced noticeably.
The performance of the engine will be similar to normal conditions.
The turbochargers cooling water flow will increase.
The cylinder cooling water flow will increase.
Why is it necessary to have an effective ballast water management plan which includes provision for changing out ballast in open water rather than discharging ballast in coastal waters?
To avoid the introduction of non-indigenous species of marine life from one area to another.
To keep the ballast water fresh in the ballast tanks during long voyages.
To allow ballast tank inspections to be carried out during ballast passage.
To ensure that ballast tanks are always pressed up during a ballast voyage to avoid free surface effects.
What should be the healthy continuity resistance of a 220V, 2,2kW, 10A heating element, when checked near to it’s rated operating temperature?
How can a lead-acid type battery be checked to confirm if it is fully charged or not?
Measure the relative density (specific gravity) of the electrolyte.
Measure the battery voltage.
Measure the level of the electrolyte.
Measure the temperature of the electrolyte.
During maintenance work on the main engine a problem arises regarding the lifting of a main component in that the manufacturer’s instructions ado not apply to the engine as fitted and present a hazard. In which of the information/record sources given in the options, is it most important to record the information relating to this anomaly?
ISM procedures in the ship’s safety manual.
Engine room planned maintenance schedule.
How can the pressure be regulated during start up of a positive displacement pump such as a gear pump?
Adjustment of the pressure relief valve to recirculate part of the flow.
Positive displacement pumps operate at constant pressure and cannot be regulated.
By throttling the discharge valve.
By throttling the suction valve.
The engine turns over normally when starting air is supplied but does not fire even though normal starting rpm is achieved. What could be the probable cause to this?
Air in the fuel oil system.
The lubricating oil temperature is low.
The turbocharger has not run up to normal full speed.
The turning gear interlock has operated.
Some ships generate electrical power at 440 V, but then step up this voltage to supply specific electrical equipment. One common example, may be to feed a large bow thruster. Why is this done?
The overall ship’s electrical load does not justify a High Voltage generating plant. This method allows more power to be delivered to the bow thruster at low running cost.
Manufacturers can supply High Voltage bow thrusters at less cost, and the power factor is improved.
A large bow thruster will draw very large currents at low voltage. Being typically remote from the generator, significant voltage drops would occur at low voltage.
The shipyard could not purchase a High Voltage generating plant at the time of manufacture, so they used what was available at the time.
A transformer overheats while taking a shore supply. Which is the likely cause?
When measuring level of liquids with a conductivity level indicator, measurement is performed by:
What is the result of an “unusually large metacentric height”?
The vessel will roll slowly or be unstable.
The vessel will have a great bending moment.
The vessel’s tweendeck heights is too high.
The vessel will roll violently.
The muster list shall show the duties assigned to the different members of the crew. Which of the given duties necessarily have to be included in the muster list?
Preparation and launching of survival crafts.
Type of fires that can be encountered on board.
Preparation and starting of emergency generator.
A ship’s electrical system operates at 60 Hz, but when connected to shore supply it is supplied with 50 Hz. Which of the following would you expect?
Electric motors will run at reduced speed, and will tend to overheat.
Earth faults are more likely.
Electric motors will run at increased speed and will tend to overheat.
Generators are more sensitive to reverse power faults.
The main engine is running steady with an average exhaust gas temperature of approximately 350 °C. What would be a typical alarm/slow down setting for the cylinder exhaust gas temperature deviation from the average?
A triac is used to provide temperature control of an oven. The galley complains that the oven only reaches approximately 50 % of demanded temperature. Which of the following is a likely cause?
The triac has completely failed.
The voltage supply to the oven controller is reduced by about 50 %.
Connection between the demand knob and the triac gate terminal has gone open circuit.
One of the main switching elements in the triac has failed.
A motor nameplate reads 75 hp. What is the reading in kW?
In tanker operations, there will be some areas and zones where flammable or explosive vapour, gas, or dust may be expected. Such areas are classified as hazardous. What is meant by hazardous area Zone 1?
Flammable mixture is continuously present or present for long periods.
Flammable mixture is not continuously present, but will be present during normal operations.
Flammable mixture is not present at all times.
Flammable mixture would not normally be present or it would be present for a short period only.
In what kind of measuring equipment might we find a Bourdon-tube?
In a pressure transmitter.
In a temperature transmitter.